139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo.

2nd floor – 75% of cabinetry is complete. 75% of flooring is done. Painting contribution is 75%. Baseboard installation has begun and is approximately 25% complete. Lighting fixtures are installed in 75% of units. Plumbing fixtures are on site and 20% have been installed. Interior doors and hardware installation has begun. 100% of HVAC units are complete.

3rd floor – Painting is 75% complete. 100% of flooring is on site and has been installed in 20% of units. Cabinetry is 40% complete. 75% of unit have lighting fixtures installed. Plumbing fixtures will arrive on site by month end. HVAC for all units have been installed.

4th floor – Wood work and interior doors are 75% complete. Window casings are 75% installed. Painters are working diligently and completed 40% of units. 75% of HVAC units are installed. Electrical and plumbing rough ins are done and inspected.

PH floor – Drywall is 100% complete. Taping has 75% done. Electrical and plumbing rough ins have passed all city of Winnipeg inspections. Painting is to commence by month end.

Exterior work – Corner unit curtain wall windows are on site and currently being installed. We anticipate completion by month end. The application of acrylic stucco is ongoing and is approximately 25% complete. Masonry prep work is 50% complete and the material is currently on site. We expect Masonry work to begin by mid-June

Now that all of our mechanical and electrical contribution is complete throughout the building, we have been able to determine the number of storage rooms available for purchase. The price will be $15,000 per room.

1 room available on the 2nd floor
2 rooms available on the 3rd floor
3 rooms available on the 4th floor
2 rooms available on the PH floor

Much like a parking stall, after purchased, the storage rooms will be assigned to a unit’s title with an exclusive use agreement. The storage rooms can be sold or transferred accordingly. They will have a private entrance with a separate lock. Rooms are approximately 88 sq/ft with a 9 or 10ft ceiling height (dependent on floor). With only 8 units available, we are not limiting rooms to be purchased by residents on their floor.

We have received many inquiries regarding possession dates. We meet weekly with all trades to determine site schedules and ultimately the completion of each trade’s contribution. Our latest update with our trades indicates possession dates will commence in the month of August 2019. Residents will be moving in floor by floor, beginning with the 2nd and moving up. We can accommodate a maximum of 2 move-ins per day. A deficiency walkthrough of your unit will be scheduled approximately 3 weeks prior to possession. During the walkthrough we will identify any deficiency’s in your unit. Our goal is to have the majority of the deficiencies repaired prior to your move in date.

Sincerely,

Myles Kraut
President – Karma Development

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. 2nd floor drywall, taping, mudding and painting now 100% complete, and the finishing carpentry has been finished. Millwork installation is 50% done with flooring install to begin next week. Final electrical and lighting installation has begun and 50% of HVAC units are now in place. 3rd floor drywall, taping and mudding are complete and 50% of the units have been painted. The finishing carpentry is 50% done. 4th floor plumbing is now 100% complete. Drywall is finished and taping has begun. Finishing carpentry contribution is going to commence next week. 5th floor electrical rough-ins are 90% finished and the plumbing contribution is 75% complete. HVAC rough-ins have been installed and exterior insulation is to begin next week.

Acrylic and masonry contractors are on site preparing for the season. Scaffolding is to be installed on the west side of the building by month end. Temperature permitting, we hope exterior work can begin next month.

There are still a number of owners with an outstanding balance at one or more of the suppliers. If you are unsure if you have an amount owing, please contact the suppliers directly to coordinate payment.

Sincerely,

Myles Kraut
President – Karma Development

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. Environment Canada claimed this past winter had the coldest average temperature in the past 40 years. We are proud to say this did not hinder our development and are very pleased with the progress made. The drywalling and taping is now complete on the 2nd floor. 3rd floor plumbing is 100% complete. Drywall is 20% and is expected to be finished by month end. 4th floor plumbing contribution is 90% done. The framing and HVAC on the PH are both 100% finished. Electrical is 50% and plumbing 25% complete. Common area electrical, heating and cooling and plumbing contributions are 25% complete. The elevators are both installed and upon a successful inspection, operational.

We want to provide one additional reminder to those of you that have been contacted by our trades/suppliers and have not yet fulfilled their request for deposit or payment, please do so as no materials can be ordered until the appropriate funds have been issued. This may result in a price increase in your quote and/or significant delays in your possession. If you are unsure if you have an outstanding balance, please contact the suppliers directly to coordinate payment.

Sincerely,

Myles Kraut
President – Karma Development

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. The cold weather has not hampered our progress over the past two months as the vast majority of work remaining is indoors. All 2ndfloor terraces are waterproofed and sealed. In addition, all City of Winnipeg inspections are complete, drywalling is well underway and taping has begun. floor plumbing is finished with all tubs and showers bases in place. 3rdfloor inspections are complete and all units have been insulated. Custom plumbing and framing finishes are 90% complete. 4thfloor electrical, including inspections, is 100% complete. Framing is 100% complete and the install of insulation has begun. Pluming is 75% done. PH unit customizations have been submitted to all trades and are currently ongoing. Framing is 90%, HVAC contribution is 70%, electrical 10% and the plumbing contribution has begun. Roof insulation and membrane are both complete. Common area electrical, heating and cooling are all underway.

For those of you that have been contacted by our trades/suppliers and have not yet fulfilled their request for deposit or payment, please do so as no materials can be ordered until the appropriate funds have been issued. This may result in a price increase in your quote and/or  significant delays in your possession. If you are unsure if you have an outstanding balance, please contact the suppliers directly to coordinate payment.

We would like to remind you one final time. Under no circumstance can any owner go on site without permission from Karma.This puts us at risk of the entire site being shut down for violating safety practices. More importantly the danger of those going on site without the proper equipment, putting themselves at risk of getting injured. Again, no owner is allowed on site without the accompaniment of a Karma employee. As always please feel free to contact us if you have any questions or concerns.

Sincerely, 

Myles Kraut

President – Karma Development 

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. We are extremely happy with the progress we have made in November as December is typically a short month due to the holiday season.  We currently have approximately 60 work people working diligently on the interior of the building. The parapet walls are now in place with the roof insulation and membrane 50% complete. We have successfully enclosed the building with 100% of the windows installed. Temporary heat has been implemented on the 2nd and 3rd floor to keep everyone on site warm and allow productivity to keep pace. Our framers have completed the 4th floor and are 50% done the PH. The electrical contribution on the 2nd floor is complete and is ready for our January 2019 inspection. The 3rd floor is 95% and 4th floor is 20% complete. The plumbing contribution is also finished on the 2nd floor and ready for our January 2019 inspection. The 3rd floor is 90% and the 4th floor is 20% complete.

We have sent out the 4th floor framing, electrical and plumbing charges and ask that everyone reviews and mails or drops off payment to the Karma office. The PH is still under review and will be sent out in the new year.

It has come to our attention that a number of owners have been stopped while attempting to go on site to view their unit. Under no circumstance can any owner go on site without permission from Karma.This put us at risk of the entire site being shut down for violating safety practices. More importantly the danger of those going on site without the proper equipment putting themselves at risk of getting hurt. Again, no owner is allowed on site without the accompaniment of a Karma employee.

We hope everyone has a wonderful holiday and new year.

Sincerely,

Myles Kraut

President – Karma Development

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. We are extremely pleased with the quality of work to date and the synergy between trades on-site. We currently have approximately 75 work people braving the elements as we work towards enclosing the buiding. The weather membrane sealant is now 100% complete. The roof is in place and the parapet walls are 50% complete. The framing on the 2ndand 3rdfloor is complete. The 4thfloor framing is 85% done and the 5thfloor framing has begun. The plumbing rough-in is 95% complete on the 2ndfloor and 60% on the 3rdfloor. The 4thfloor rough-in has begun. The 2ndfloor electrical contribution is now 100% complete. The 3rdfloor electrical is 75% with the 4thfloor scheduled to commence in the last week of November. 100% of the balconies have been installed. Approximately 50% of the windows have been installed with the remainder to be done by November 30th.. The parkade is complete and currently being heated. As I’m sure many of you have noticed all of the heavy for our project is done, hence the removal our large tower crane.

We are currently finalizing the 4thfloor framing, electrical and plumbing changes in order to identify any final costs associated with any upgrades. Invoices will be sent out by mid-November. We have met with the electrician, framer and plumber and are currently reviewing all 5thfloor work.

A few of units are still working through some final details. With framing, electrical and plumbing currently ongoing, finalizing your plans is becoming urgent. We ask for everyone to please finalize any outstanding details as soon as possible.

Sincerely,

Myles Kraut

President – Karma Development

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. We are pleased to inform you that despite the rainy month, we were able to make good progress and have over 60 work people on site daily. The exterior walls are currently being treated with a weather membrane sealant with an expected completion date of Oct 13th. 100% of our concrete is poured and in place. Framing is complete on the 2nd floor. The 3rdand 4thfloor framing is underway. The 2nd floor plumbing is 90% complete with all bathtubs and shower bases in place. 3rd floor plumbing is 20% complete and the 4th floor plumbing has been laid out. 2nd floor electrical is 80% complete and the 3rd floor electrical contribution has begun. Balconies are currently being installed, we anticipate a mid-October completion date. The roof is 40% complete and construction is ongoing. Window installation begun today and will take approximately 45 days to complete. Furnaces in the parkade are to be installed this week. We anticipate the removal of the large crane by month end. 

We are currently finalizing the 3rd floor electrical, framing and plumbing changes in order to identify the final costs associated with any upgrades. All final quotes for electrical will be provided by SuperLite. The final quotes for the framing and plumbing will be provided by Karma and should be completed and sent out by mid-October. We have met with the electrician, framer and plumber and are currently reviewing all 4th floor work. 

2nd, 3rdand 4thfloor final review meetings are now complete and we are currently scheduling and conducting our review on the PH suites. A reminder to please bring all contracts, invoices and documents relating to your unit and upgrades to ensure all details are documented during your review.  

Sincerely,

Myles Kraut   

President – Karma Development

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. We are quite happy with the progress that has been made this month. I am pleased to inform you that the 2ndfloor concrete is now 100% complete. The 3rdfloor concrete is now 50% complete and we anticipation moving onto the 4thfloor by month end. The 3rdfloor walls are prepped and have begun to be erected.  We have prepped the 1stsection of the parkade for a concrete pour and will be completed by mid August. The balance of the parkade will be completed by month end. Electrical is 50% complete in the parkade. Plumbing in the parkade is now 100% complete with work set to commence on the 2ndfloor by month end.

We have completed all 2ndand 3rdfloor final reviews and are currently underway with the 4thfloor units. We would like to remind everyone again to please bring all contracts, invoices and documents relating to your unit and upgrades to ensure all details are documented during your review. We expect to complete all 4thfloor reviews and the 50% of PH units by the end of August.

We are currently working on all 2ndand 3rdfloor changes that have been made to electrical, plumbing or framing in order to identify any final costs associated with those upgrades. Now having met with the electricians, plumbers and framers, we have noted all changes and are working to provide final quotes associated with your changes. Once the 4thand PH final reviews are complete, we will meet with the electricians, plumbers and framers again to go through all remaining changes and work to provide the remaining quotes. We ask and appreciate your patience, as our goal is to mitigate the risk of any errors and will need some time after our meetings to provide these final quotes.

BA Robinson has begun to contact everyone to collect overages for any upgrades made. Due the significant backlog of orders with the manufacturers, we are placing our final order with BA Robinson at the end of August. For those who have made any changes with BA Robinson, please contact them as soon as possible to provide payment.

We would like to thank everyone who has finalized all changes prior to their final review thus far. A few 4thfloor and PH units are still working to finalize their selections, we would like to remind you that this is the last opportunity to complete your changes. Failure to do so will revert any desired changes to the standard package from that supplier.

Sincerely,

Myles Kraut

President – Karma Development

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. I hope everyone has been enjoying the beautiful weather we have had lately. I am please to inform you that all stairs have been placed in the stairwells. The steel beams, exterior structural walls and the floor joists on the 2ndfloor are now complete. The 2ndfloor terraces are currently being poured and will be completed by month end. Once the terraces are complete, the 3rdfloor structural walls will be prepped and begin to be erected. We are currently prepping the parkade floor to pour concrete. Electrical and plumbing work has begun in the parkade.

We are currently undergoing our final review meetings with each unit. The 2ndfloor unit reviews are now complete and we have met with approximately 50% of the 3rdfloor units. The 3rdfloor meetings should be scheduled and completed in the next 2 weeks. We would like to remind everyone to please bring all contracts, invoices and documents relating to your unit and upgrades to ensure all details are documented during your review.

We have received the majority of sign offs from Interior Illusions and from our independent suppliers. However, there are still a few units that are outstanding. We ask everyone who is still working to wrap up the last few items to do so as soon as possible. If you are unable to sign off by your final review, we will be unable to implement those changes and will revert back to the standard package. As mentioned last month, we will be confirming any changes that have been made to electrical, plumbing or framing in order to identify any final costs associated with those upgrades.

Sincerely,

Myles Kraut

President – Karma Development

139 Tuxedo Update

Dear Future Residents,

Welcome to your latest update for 139 Tuxedo. I am please to inform you that the 5th floor stairwells are now 100% complete. All foundation work has been completed. The elevator shafts are now complete. Permanent hydro is up and running. With all of the prep work now complete, we have begun erecting the steel superstructure. This process should take approximately three months, during which time we will be installing all windows and glazing. Electric and plumbing will be underway shortly.

We would like to thank everyone who has successfully signed off on the selections of your finishing materials. It was a long journey for many, but we appreciate your efforts in completing your part for the end of May. For the few who still have items outstanding, Karma is working diligently with the suppliers to provide the information you require as soon as possible so that you can finalize your selections. For those who have not contacted Michelle or our suppliers thus far, your unit will be provided with the finishing materials found in our presentation centre.

We will begin contacting each of you next week to setup your final review meeting. We will begin with the 2nd floor and continue meetings with the 3rd, 4th and PH floors respectively. This meeting will be going over every selection made with each supplier to mitigate the risk of any errors. As well we will be confirming any changes that have been made to electrical, plumbing or framing in order to identify any final costs associated with those upgrades.

Sincerely,

Myles Kraut

President – Karma Development